A-to-Z plan for a solo developer

hyperdot.ps1 plan tracks a game from first idea to post-launch as seven phases with gates. This page explains where the pipeline comes from and why the gates are what they are. Commands: plan -Do init [-Profile jam] | status | done -Id <gate> | reopen -Id <gate>, tasks with add | move | remove | link | sync, all with -Json (see json.md).

Where it comes from

Three inputs, cross-referenced:

  1. The Mehendysis GDD development plan: a studio-scale template - pre-production (2 mo), production (12 mo, four milestones), testing (3 mo, alpha then closed/open beta), polish and launch prep (2 mo), post-launch - with risks (technical, creative, market) and mitigations. Its shape is kept; its team of 15 and 19 months are scaled down to one person.
  2. The Work Loop board (a kanban template): Backlog -> Design -> To Do -> Doing -> Testing -> Done (the template also uses Code Review, with a list limit as a signal to finish reviews before starting work). Kept as the daily loop: plan.json tasks use backlog, design, todo, doing, verify, done and wipLimit caps doing. "Verify" is where the test suite and an agent review replace a human code reviewer.
  3. Public solo-dev guidance (weak evidence, mostly blogs and vendor posts; used for shape, not numbers):
    • milestone ladder prototype -> vertical slice -> content-complete -> beta -> gold, each retiring one risk; when one slips, cut scope, not testing (Bugnet, Wayline);
    • prototype tests whether the core loop is fun; a stranger playing 15 minutes and wanting more is the evidence (Bugnet);
    • vertical slice as a PROCEED/PIVOT/KILL gate before production (Claude-Code-Game-Studios skill);
    • a timebox on the slice, and a scope ladder (MoSCoW) set up front (Wayline);
    • Steam "Coming soon" page months before launch, because wishlists compound and each becomes a launch-day notification; one Next Fest per game (Wayline checklist, Presskit field guide).

The phases

# Phase Weeks* Question it answers Automatic gates
1 Concept 2 What is it, and what is it not? docs/GDD.md exists; docs/RISKS.md written; docs/BUDGET.md (optional)
2 Prototype 4 Is the core loop fun? CI workflow wired; docs/TRAILER.md exists; docs/DECISIONS.md has the verdict
3 Vertical slice 8 Can I build and ship one polished piece? a test runner detected; an export preset exists; docs/TECH-DEBT.md exists
4 Production 24 Can I build the rest as playable milestones? docs/MILESTONES.md exists
5 Alpha and beta 8 Is it stable, fair, accessible? no placeholders left; tests green
6 Release candidate and launch 4 Does a clean export run, and can players find it? export preset
7 Post-launch 8 What do players hit, and what next? docs/RETRO.md exists

*Defaults for about 10 hours a week; the slice gate re-sizes the rest from measured velocity. Edit timeboxWeeks, add or remove gates freely: plan.json is yours after init. A manual gate marked done too early opens again with plan -Do reopen -Id <gate>; an automatic gate opens by itself when the project stops meeting it.

Automatic checks: tests (a test framework's runner is detected), ci (a GitHub workflow calls the kit's reusable workflow or composite action, or .gitlab-ci.yml includes its GitLab template), preset (an export preset exists), runner:<name> (that runner is set up), file:<path> (a folder, or a file that is not empty: an empty docs/RISKS.md is not a risk log; the path is looked up from the repository root, then the Godot project) and placeholders (nothing is left as a placeholder: no assets.json entry has "placeholder": true and the Placeholders table of docs/TECH-DEBT.md has no row; with neither file, nothing says what is left, so it stays open). A gate with "optional": true (concept.budget) is listed while open but does not hold its phase back.

Rules baked into the gates

Tasks and the GitHub Project

Day-to-day work lives in plan.json tasks, edited with commands so an agent cannot corrupt the file:

pwsh ci/godot/hyperdot.ps1 plan -Do add -Title "Paddle feel pass" -Column todo
pwsh ci/godot/hyperdot.ps1 plan -Do move -Id t1 -Column doing      # refused past wipLimit
pwsh ci/godot/hyperdot.ps1 plan -Do move -Id t1 -Column "To Do"    # a column name works too
pwsh ci/godot/hyperdot.ps1 plan -Do move -Id t1,t2,t3 -Column done  # several in one call: all move or none (each call reads the project)
pwsh ci/godot/hyperdot.ps1 plan -Do remove -Id t1                  # delete a task

Columns map onto the Work Loop: backlog Backlog, design Design, todo To Do, doing Doing, verify Testing, done Done. -Column (in add, move and link) takes a column id or the name of the project column it maps to, case-insensitive and by prefix as sync matches options, so "to do" and "Done ๐ŸŽ‰" work; plan.json always stores the id. remove deletes a task; a removed task's id is never given again (lastTaskNumber), and its item is archived by the next sync (project.toArchive).

GitHub Project sync (plan -Do sync) is experimental: it has met only a stand-in gh so far (the live run waits, and the open items are under GitHub Projects in roadmap.md). It keeps the plan the source of truth and uses a GitHub Project as the place you drag things. It needs the GitHub CLI signed in with the project scope (gh auth login, then gh auth refresh -s project; or GH_TOKEN holding a token with that scope). The kit never reads or stores the token.

Setup is one command. plan -Do sync -Board @me (or -Board <login> for another user or an organisation) makes a private project titled " plan", adds a single-select field Column with the six columns above, links the project to the game's GitHub repository when its git origin is on github.com, puts one item per task in its column, and saves project.owner and project.number in plan.json. GitHub's built-in Status field offers only Todo, In Progress and Done and the CLI cannot change its options, so the kit adds its own field; set the project's Board view to group by Column once (gh project view <number> --owner <owner> --web; the CLI cannot create or edit views). To use a project that already exists, plan -Do link -Board <owner>/<number> (a project URL works too) or plan -Do sync -Board <owner>/<number>.

After that plan -Do sync with no arguments:

Item ids are the project's node ids (PVTI_...; gh project item-list <number> --owner <owner> --format json shows them): plan -Do link -Id <task> -Item <id> -Column <column> ties a task to an item made by hand. Options are matched by name prefix, so Done ๐ŸŽ‰ matches done; override per column under project.columns in plan.json (sync and link -Board keep it). A task in a column the plan does not have stops the sync before any call.

The plugin's second Stop hook (hooks/project-sync.ps1) runs the same sync after a turn that changed the plan's tasks and the plan has a project, so the board follows without anyone asking. It keeps a hash of what it last synced in .godot/hyperdot-project-sync (an unchanged plan costs no call), never blocks the turn, and turns a failure into a one-line notice. HYPERDOT_PROJECT_SYNC=off disables it.

tests/Test-ProjectSync.ps1 runs these steps (and the hook) against a stand-in gh on every change, and with -Live against GitHub with a private project it creates and deletes (the Project sync workflow, with a HYPERDOT_PROJECT_TOKEN repository secret: a personal access token with the project scope, since the workflow's own token cannot reach a user's projects).

Release dates

Steam's dates depend on each other, and a missed one moves the release. plan.json has an optional release block (dates as yyyy-MM-dd, null until known), and plan and status warn when a rule from store-and-legal.md cannot be kept; they never fail:

Field Meaning Warns when
date The planned release day; nothing is checked without it -
steamFeePaid When the Steam Direct fee was paid fewer than 21 days before date, or unset with fewer than 21 days left
comingSoon When the Coming Soon page went (or goes) live fewer than 14 days before date, or unset with fewer than 14 days left
storePageSubmitted When the store page went to review fewer than 7 business days before comingSoon, or unset with fewer left
buildSubmitted When the build went to review fewer than 7 business days before date, or unset with fewer left; before storePageSubmitted (the page is reviewed first)
nextFest The first day of the Steam Next Fest the game takes part in on or after date (do the last Next Fest before launch)
demoSubmitted When the Next Fest demo went to review after 3 weeks before nextFest (5 with pressPreview), or unset once that day has passed
pressPreview true when the demo is in the press preview -

Reviews take 3 to 5 business days, so the kit asks for 7; business days are Monday to Friday (public holidays are not known to it). From two weeks before date the release date is locked on Steam, which plan notes. plan -Json returns the timeline as release (json.md): days and business days left and each deadline.

The GDD, status and /game

docs/GDD.md (template: ci/godot/templates/GDD.md) is the game's scope. Features are headings of the form ### F3 Lives and game over, each with a Priority: line (must, should, could, won't) and Done when: bullets. Tests that prove a feature carry a GDD:F3 tag in their name or a comment; examples/csharp shows the convention. The other sections (audience and expected rating, the loop at three scales, the first session step by step, world rules, what failing costs, content counts and length, open questions, changes) are for people and agents; status reads only the pitch and the features.

status -Json reads all of that, plus the plan, the latest runs, git activity and an inventory of the project, without judging anything (json.md). The game skill (/game) does the judging; start every session with it:

  1. the first time, it drafts the GDD from the code and confirms it with you section by section;
  2. it marks each feature missing, started, works or proven, with evidence, in plan/STATUS.md, with a short design and architecture review: at most five problems with their evidence (features that serve no kind of fun, scope drift, architecture warnings, autoloads no decision covers, subagent verdicts nobody acted on);
  3. it adds a plan task (plan -Do add -Feature F3) for each feature that is not proven;
  4. through plan -Do sync (experimental), it creates and moves project items. An item you moved since the last run keeps your column: each task records the column its item was in (boardColumn), so an item that is somewhere else was moved by you;
  5. it ends with the three best next tasks to pick from.

Scope rule: before building anything the GDD does not contain, the agent asks whether to add it as a feature or drop it.

The weekly-review skill writes plan/reviews/<date>.md (done, health, phase, risks) and proposes next week's tasks. It also reads docs/kit-notes.md, the line the agent appends each time the kit got in the way (init -Agents creates the file), and proposes up to three kit changes for you to approve; approved ones become kit pull requests through /retro, never on their own. Run it every Friday as a local scheduled task in the Claude desktop app, which can reach the game folder, the kit and the GitHub CLI at once (a cloud task gets only a fresh clone of a GitHub repository):

  1. Code tab โ†’ Scheduled โ†’ New task โ†’ Set up manually.
  2. Name weekly-review; instructions: Run the weekly review of this game (the weekly-review skill).
  3. Advanced settings โ†’ turn on Only on this computer; Local folder: the game folder.
  4. Trigger: Weekly, Friday, the time you want (local time, so Athens time on an Athens PC).
  5. Create it, then Run now once and choose "always allow" for the kit's commands, so later runs do not stall on prompts.

It runs only while the app is open and the computer awake; a missed Friday runs once when the PC wakes. The skill is not manual-only on purpose: a scheduled prompt can start only skills Claude is allowed to invoke.

Jam mode, risks, money and exit criteria

game-plan also covers what the gates only point to:

Not covered (yet)

Team roles and live-ops staffing from the studio template (a solo plan has one role). Platform certification for consoles. Regional ratings. Add them as gates in plan.json if they apply.